Skip to main content

(2024) All Malaysia Reports (AMR) - Week 32

/
Content updates

Recently added cases from AMR to Westlaw Asia

Firdaus Khan bin Parit Khan & Anor v CIMB Bank Berhad [2024] 5 AMR 793, CA

Civil procedure – Appeal – Memorandum of appeal ("MA") – Application for extension of time – Record of appeal filed within stipulated period – MA omitted as High Court's written judgment ("judgment") not provided – Supplemental record of appeal containing MA filed after availability of judgment – Whether appeal ought to be dismissed for breach of rule 18(7) of the Rules of the Court of Appeal 1994 ("RCA") – Whether rule 18(7A) of the RCA prevails over rule 18(7) thereof – Whether there was agreement between parties for MA to be filed only after judgment received – Whether rule 105 of the RCA ought to be invoked to decide such application – Whether appellants would be prejudiced if application dismissed – Whether application ought to be allowed – Rules of the Court of Appeal 1994, rules 3A18(7), (7A), (7B), 93, 94, 102, 105

Civil procedure – Time – Enlargement or extension of – Application for extension of time to file memorandum of appeal ("MA") – Record of appeal filed within stipulated period – MA omitted as High Court's written judgment ("judgment") not provided – Supplemental record of appeal containing MA filed after availability of judgment – Whether appeal ought to be dismissed for breach of rule 18(7) of the Rules of the Court of Appeal 1994 ("RCA") – Whether rule 18(7A) of the RCA prevails over rule 18(7) thereof – Whether there was agreement between parties for MA to be filed only after judgment received – Whether rule 105 of the RCA ought to be invoked to decide such application – Whether appellants would be prejudiced if application dismissed – Whether application ought to be allowed – Rules of the Court of Appeal 1994, rules 3A18(7), (7A), (7B), 93, 94, 102, 105

Residenmas Development Sdn Bhd v YM Raja Halinuddin bin Raja Halid [2024] 5 AMR 817, CA

Contract – Assignment – Breach – Income and payments due from developer to main contractor under construction contract allegedly assigned to plaintiff vide bailout and temporary take over agreement ("agreement") – Plaintiff's claim against developer for outstanding sums due to main contractor allowed by High Court – Whether agreement between main contractor and plaintiff amounted to absolute assignment – Whether plaintiff being stranger to the construction contract had locus standi to seek sums arising thereof – Whether appellate intervention warranted – Civil Law Act 1956, s 4(3)

Anjung Hijau Sdn Bhd v Associated Builders & Contractors Sdn Bhd & 2 Ors [2024] 5 AMR 835, HC

Contract – Construction contract – Extension of time ("EOT") – Validity of – Suit filed by developer for declaration that EOTs granted for completion of residential project were null and void – Counterclaim by contractor for unpaid works – Whether EOTs invalid and contrary to PAM Contract 2006 (Without Quantities) standard form contract – Whether developer entitled to liquidated ascertained damages – Whether contractor entitled to payment for works done – Whether developer, architect and project engineer guilty of conspiracy against developer in granting EOTs – Evidence Act 1950, ss 101, 102

Khatimah binti Irin (suing as administrator to the estate of Hamzah bin Abdul Hamid) & Anor v AIA Berhad [2024] 5 AMR 866, HC

Civil procedure – Amendments – Statement of defence ("SOD") – Insurer repudiated deceased's insurance claims via repudiation letter based on material misrepresentation – Discovery of hospital documents revealed non-disclosure of deceased's smoking habit – Insurer applied for amendment in SOD to insert new revelation – Deceased's family opposed application on grounds of delay and proposed amendment amounting to new ground of repudiation – Whether proposed amendment introduces new and distinct ground – Whether there was delay in filing application – Whether application ought to be allowed – Evidence Act 1950, s 3 – Rules of Court 2012, Order 20 r 5

Professor Dato’ Dr Sellappan s/o Subbiah v Datuk Subbiah s/o Thevarayan Chettiar & 2 Ors [2024] 5 AMR 874, HC

Contract – Specific performance – Family settlement agreement – Plaintiff claimed specific performance of quadripartite agreement entered by family members – Agreement unilaterally terminated by first defendant due to plaintiff's alleged breach – Whether agreement irrevocable and binding – Whether termination valid – Whether plaintiff breached agreement – Whether plaintiff's alleged breach goes to root of agreement, attracting application of ss 40 or 56 of the Contracts Act 1950 – Whether plaintiff's action barred by doctrine of laches – Whether agreement unenforceable against third defendant on grounds of his ignorance and/or lack of consideration and/or undue influence – Whether action ought to be allowed – Contracts Act 1950, ss 40, 50 – Specific Relief Act 1950, ss 11, 18, 41

Contract – Termination – Family settlement agreement – Plaintiff claimed specific performance of quadripartite agreement entered by family members – Agreement unilaterally terminated by first defendant due to plaintiff's alleged breach – Whether agreement irrevocable and binding – Whether termination valid – Whether plaintiff breached agreement – Whether plaintiff's alleged breach goes to root of agreement, attracting application of ss 40 or 56 of the Contracts Act 1950 – Whether plaintiff's action barred by doctrine of laches – Whether agreement unenforceable against third defendant on grounds of his ignorance and/or lack of consideration and/or undue influence – Whether action ought to be allowed – Contracts Act 1950, ss 40, 50 – Specific Relief Act 1950, ss 11, 18, 41

 

By Thomson Reuters Malaysia Editorial Team
Malaysia Editorial Team

Speak to a consultant

Can't find an answer to your question?
Contact our support team.

Request training

Contact our team to arrange training.

Tell us what you think

We'd love to hear what you think
of our products and support.